Friday, March 11, 2011

Important Fukushima update/Emergency Declared at Japanese Nuclear Plant

On Behalf Of Michael Mariotte
Friday, March 11, 2011 3:44 PM

Here is an important new update to NIRS fact sheet on Fukushima. Full, periodically updated factsheet available at http://www.nirs.org/reactorwatch/accidents/Fukushimafactsheet.pdf.

 

UPDATE, 3:30 pm, Friday, March 11, 2011: A Japanese Cabinet Office report released at 12:30 am Saturday, March 12, 2011 (Japanese time) predicts that fuel damage will occur at the Fukushima Daiichi Unit-2 reactor late Saturday night (Japan time, early Saturday morning US time) if cooling is not restored before then.

 

Environmental activists in the area report that radiation monitoring stations in the Fukushima Daiichi area are not operating. Tepco's (Tokyo Electric Power Co.) monitoring website is at http://www.tepco.co.jp/nu/pamp/index-j.html

 

At the top it says that "monitoring goes on around the clock year round". At the bottom it says in red: THIS SYSTEM IS CURRENTLY SHUTDOWN.”  Activists believe this is indicative of an attempt to downplay potential radioactive releases, especially as Tepco says it plans to vent the containment to relieve pressure, which will cause release of radioactivity into the air.

 

http://www.nytimes.com/2011/03/12/world/asia/12nuclear.html?hp=&adxnnl=1&adxnnlx=1299865504-GM66++wmf9RA1iYs+VfByw

 

The New York Times

March 11, 2011

Emergency Declared at Japanese Nuclear Plant

By MATTHEW L. WALD

The Japanese government declared an “atomic power emergency” and evacuated thousands of residents living close to a nuclear plant in northern Japan after a major earthquake, but officials said there had been no radiation leak from the facility and that problems with its cooling system were not critical.

The company that operates the plant, Tokyo Electric Power Co., said however that it was planning to release slightly radioactive vapor to reduce pressure inside a reactor.

Some 3,000 people were told to leave a 2-mile radius around the Fukushima No. 1 plant, located in Fukushima Prefecture, after a mechanical failure in the cooling system, government officials said.

The plant is designed to shut down safely after an earthquake, but its emergency diesel generators, needed to run water pumps, were not working. American experts on reactors of the Fukushima design said, though, that technicians at the plant would have several hours to restore power before any significant damage resulted.

Japan’s nuclear safety agency attributed the expected release of vapor to pressure inside one of six boiling water reactors at the plant rising to 1.5 times the level considered normal, according to The Associated Press. Yuichi Nagano, the deputy manager of Tokyo Electric’s Washington office, said the vapor would be slightly irradiated, though it would pass through filters before being vented. The nuclear safety agency said the release should not pose a threat to people’s health.

The evacuation was described as precautionary. Near midnight Japan time on Friday, Jiji Press, a Japanese news agency, quoted Trade Ministry officials as saying that the cooling system would be reactivated and should resume normal operations.

Japan relies heavily on nuclear power, and it generates just over a third of the country’s total electricity. The facilities are designed to withstand earthquakes, which are common in Japan, but experts have long expressed concerns about safety standards at the plants, particularly about the impact a major quake could have if it hit close to a reactor.

At least two other Japanese nuclear plants also reported trouble, but there was no radiation leak at either of them, government officials said. A number of nuclear reactors around the hardest-hit area of the country were shut down, and Japanese news media said a fifth of the country’s total nuclear generating capacity was offline because of the quake.

One major concern is that while operators can quickly shut down a nuclear reactor in an earthquake or another emergency, they cannot allow the cooling systems to stop working. Even after the plant’s chain reaction is stopped, its fuel rods still produce heat. The production of heat drops off sharply over the following hours, but continued cooling is needed, or the water will boil away and the fuel will melt, releasing the uranium fragments inside.

Heat from the nuclear fuel rods must be removed by water in a cooling system, but that requires power to run the pumps and to align the valves in the pipes. So the plant requires a continuous supply of electricity even after the reactor stops generating its own power.

An analyst with the World Nuclear Association, a major international nuclear power group, told Reuters that he understood fresh cool water was now being pumped into the cooling system at Fukushima, reducing the threat of a meltdown.

“We understand this situation is under control,” the analyst said, adding that he understood that a back-up battery power system had been brought online after about an hour and began pumping water back into the cooling system, where the water level had been falling.

Japanese news media quoted officials in Fukushima Prefecture as saying that water levels were 3.4 meters — about 10 feet — above the fuel rods at the No. 2 reactor at the plant. Tokyo Electrical Power officials confirmed that water levels had been falling but said that fuel roads had not been exposed.

Civilian power reactors are designed with emergency diesel generators to assure the ability to continue cooling even during a blackout. Many reactors have two, assuring redundancy; some have three, so that if one must be taken out of service for maintenance, the plant can still keep running.

It was not immediately clear how many there are at Fukushima, but the operators reported earlier in the day that they were not working, prompting the evacuation.

Fukushima 1, which was designed by General Electric and entered commercial service in 1971, was probably equipped to function for some hours without emergency diesel generators, according to David Lochbaum, who worked at three American reactor complexes that use General Electric technology.

Mr. Lochbaum, who also worked as an instructor for the Nuclear Regulatory Commission on GE reactors, said he did not know the details of Fukushima, but that such reactors were equipped to ride out interruptions in electrical power by using pumps that could be powered by steam, which would still be available in case of electric power failure. Valves can be opened by motors that run off batteries, he said. Older plant designs, of the era of Fukushima, generally have batteries sized to operate for four hours, he said.

After four hours, heat production in the core is still substantial but has been reduced, he said. The heat would boil away the cooling water, raising pressure in the reactor vessel, until automatic relief valves opened to let some of the steam out. Then the valves would close and the pressure would start building again.

If the cooling system remains inoperative for many hours, the water would eventually boil away, he said, and the fuel would begin to melt. That is what happened at Three Mile Island, the reactor near Harrisburg, Pa., that suffered a partial core melt in March 1979. In that case the cause was not an earthquake, but mechanical failure, operator error and poor design, government investigators later found.

Mr. Lochbaum, who now works for the Union of Concerned Scientists, a group that is very often critical of nuclear safety standards, said that if the cooling water in the vessel was boiling away, the process of boiling enough to expose the fuel would take “hours, not minutes.”

The radioactive steam — which would become far more radioactive as the fuel began to melt — would fill the containment building, he said. That building is designed to be cooled, to keep down steam pressure and leaks. But those pumps require the main sources of power at the plant to function properly.

“If they start melting fuel, the containment integrity is going to the key in terms of what gets out,” Mr. Lochbaum said. “Their focus now has to be on getting back A.C. power” — or the main power supplies for the plant.

Ken Belson contributed reporting from New York.